The waste treatment project was on behalf of Microbac UK Ltd, the project was called WHP-HT1 Wellhead platform 1.
With the total weight of approximately 13,000 tons, the WHP-MT1 is the largest wellhead platform fabricated in Vietnam at the present. Construction activities were started in June 2010. Despite the various challenges and difficulties of the fast track project, the WHP-MT1 platform was completed on schedule at Vietsovpetro fabrication yard after over 14 months, a very short timeline for building a platform of this size. From the late days of August to early September, all major items of WHP-MT1 platform were successfully loaded out for sailaway to offshore location. This initial achievement is a result of close working and joint efforts by Bien Dong POC and other contractors who are PetroVietnam subsidiaries, such as Vietsovpetro, PVC-MS and PTSC.